CONSTRUCTION LINKED PAYMENT PLAN (for Tower 1, 2, 3, 4, 5, 6 & 7) |
On application for Booking |
10% |
Within 45 days from Allotment |
10% |
On Commencement of Construction |
10% |
On Completion of Ground floor roof slab |
7.5% + 100% Lease Rent |
On Completion of 3rd floor roof slab |
7.5% + 50 % Car Park |
On Completion of 6th floor roof slab |
7.5% + 50 % Car Park |
On Completion of 9th floor roof slab |
7.5% + Floor PLC |
On Completion of 12th floor roof slab |
7.5% + Landscape PLC |
On Casting of Top Floor Roof Slab |
7.5% + 100% ESC |
On Completion of Brick work |
7.5% + 100% FFC |
On Completion of Electrical Conduiting |
7.5% + 100% Power Backup Charges |
On Completion of Plumbing work |
5% + 100% Club membership |
On Offer of Possession |
5% + 100% IFMS |
CONSTRUCTION LINKED PAYMENT PLAN (for Tower 12A) |
On application for Booking |
10% |
Within 45 days from Allotment |
10% |
On Commencement of Construction |
10% |
On Completion of Ground floor roof slab |
7.5% + 100% Lease Rent |
On Completion of 4th floor roof slab |
7.5% + 50 % Car Park |
On Completion of 8th floor roof slab |
7.5% + 50 % Car Park |
On Completion of 12th floor roof slab |
7.5% + Floor PLC |
On Completion of 16th floor roof slab |
7.5% + Landscape PLC |
On Casting of Top Floor Roof Slab |
7.5% + 100% ESC |
On Completion of Brick work |
7.5% + 100% FFC |
On Completion of Electrical Conduiting |
7.5% + 100% Power Backup Charges |
On Completion of Plumbing work |
5% + 100% Club membership |
On Offer of Possession |
5% + 100% IFMS |